Homer’s proposed harbor expansion could cost more than $660 million, according to new calculations by the U.S. Army Corps of Engineers.
The city faces a local share totalling $184 million, including a 24% contingency, but will seek federal and state grants to offset the bulk of those costs as the project moves into the design and construction phases.
The federal share for harbor dredging and breakwater construction is $477.5 million. The City of Homer is responsible for additional features including vessel floats, uplands and parking.
As the non-federal sponsor, Homer’s share of “project first costs” — harbor construction including breakwaters, dredging and navigation aids — is an estimated $55.4 million.
The city also anticipates $90 million for local services facilities — the vessel floats and parking for harbor users — and $38.6 million in “post-construction payback.” Homer is required, per the Water Resources Development Act, to repay over 30 years 10% of the cost to build the new harbor breakwaters after construction is complete.

The city doesn’t need to come up with that much money tomorrow, or even in the next few years, according to city manager Melissa Jacobsen. Homer’s most immediate need is a 10% local match for preliminary engineering and design — $763,000.
Even that obligation is two to three years away, Jacobsen said Tuesday. First comes Corps approval of the feasibility study; the city expects a decision in March.
“It’s my understanding that the Chief’s Report will either be ‘yes’ or ‘no,’ and the city has an opportunity to weigh in at that point,” Jacobsen said.
Further forward movement also depends on Congress authorizing the expansion in 2028 through the WRDA.
“That gives us time to work with our state delegation.… Hopefully they will be supportive of providing funding like they have in the past, where they’ve split the costs with us 50/50 for these types of expenses,” Jacobsen said.
Besides state and federal grants, the city also proposes funding the harbor expansion through revenue or general obligation bonds, harbor user fees and long-term property leases.
General obligation bonds to support harbor construction would be subject to voter approval and paid back through city sales taxes. Revenue bonds would be paid back through harbor user fees.
“That’s a pretty heavy lift to put on (harbor users) for this amount of money, so that’s why general obligation bonds would probably be the way the city would go, because the services really benefit the community as a whole,” Jacobsen said.
She reiterated those decisions are years down the road.
“We’ll keep taking incremental bites at this,” she said. “As we learn more through the Chief’s Report and through project engineering and design, and what kind of support we’re going to be able to get from the federal government and the state, we’ll have a better idea of what we’re up against in a few more years.”
City officials sent a letter of intent, dated Nov. 13, to the U.S. Army Corps of Engineers reaffirming its commitment to the project as the Corps completes its feasibility study. The letter does not contractually obligate the city to the harbor expansion or associated costs.