Opinion: It’s time to move from one big dam project to smaller, affordable dam projects



Alaska stopped work on the Susitna-Watana Dam in 2014 because it is too expensive, too big, and too risky. During the current election year, some have tried to raise this project as an effective option for our state’s energy future. But Susitna-Watana remains as financially impractical today as it was more than a decade ago. Alaska’s energy future lies in smaller projects — like expanding the Bradley Lake hydroelectric facility — that are more affordable, more efficient, and more likely to succeed.

Susitna-Watana is the wrong dam in the wrong place at the wrong time. Supporters first proposed the project, 87 miles north of Talkeetna, as an energy solution in the 1950s when big dams were popular. After decades of inactivity, the state resurrected the project in 2011. Then Governor Walker stopped the work in 2014 because it was unaffordable. In 2019, Governor Dunleavy and the Alaska Energy Authority (AEA) tried to revive interest in the proposal, but the AEA’s work for the project has been mostly PowerPoint presentations. This year, lawmakers wisely removed a little-publicized capital budget amendment to spend $5 million to re-start the project. 

The dam would measure 705 feet tall—three times the size of any other dam in Alaska and nearly as tall as the Hoover Dam. No one in the United States has built a dam of this scale for over 40 years. In contrast, communities across the country are removing dams due to poor economics and harm to fish habitat. River management agencies removed 100 dams across the United States in 2025, and the lakes formed by Glen Canyon Dam and Hoover Dam on the Colorado River have some of the lowest water levels ever recorded. The current suggestions to build a multi-billion-dollar project in Alaska ignore the fiscal realities and technical risks that halted the project in the first place.

Multi-billion-dollar projects like Susitna-Watana consistently run over budget and over schedule. While 2014 estimates set the base construction cost at $5.51 billion, updated analysis by the Alaska Center for Energy and Power puts the likely cost at over $9 billion with an additional $34.2 million in annual costs for fixed operations and maintenance. According to the “Iron Law of Project Management,” mega-projects regularly go over budget, over time and under benefits. Bent Flyvbjerg, author of “How Big Things Get Done,” estimates that the average cost overrun of hydroelectric dams is 75%, which would increase the likely cost of Susitna-Watana to over $15 billion.

Finding federal funding for the project appears very unlikely. In 2023, the President approved the investment of $3.46 billion in electric grid infrastructure — the largest in our nation’s history — in 58 projects across 44 states, which is an average of about $59 million per project and $78 million per state. In contrast, the Susitna-Watana Dam is a $9+ billion project in one state. The dam would alter the natural flow of the Susitna River, endanger salmon runs and flood over 40,000 acres of game and wildlife habitat. There have been no meaningful proposals to build the dam with private funding. And if federal funding isn’t available, the greatest financial risk of a $9+ billion commitment falls squarely on our state. Indeed, the AEA acknowledges that raising over $560 million in combined state and federal funding to complete the Bradley Lake expansion by 2032 will be a major challenge. And if we succeed in raising over $560 million for Bradley Lake, that success will significantly limit our potential to raise any funding for Susitna-Watana.

Energy security and affordability demand our attention. Railbelt utilities are concerned that Cook Inlet natural gas supplies may soon fail to meet their needs. More cost-effective energy options exist. The cost of producing solar and wind power has dropped, making renewable options more affordable. Innovative micro-grid systems offer more efficient solutions. And smaller-scale energy projects like in-river hydropower can serve local communities without the transmission costs associated with more expensive, distant, and risky mega-projects.

Our state has already spent over $200 million pursuing Susitna-Watana across decades of study. We should not spend scarce capital funding on a risky, failed mega-project. Alaska should focus our energy investments on small, efficient, and innovative energy projects.

Sen. Matt Claman represents West Anchorage in the Alaska State Senate, is a member of the Senate Bipartisan Majority and chairs the Senate Judiciary Committee.

Discover more from The Homer Independent Press

Subscribe to get the latest stories sent to your email.

Subscribe for FREE to get HIP!

Get weekly newsletters and breaking news sent to your inbox

(after you hit "subscribe," check your inbox to confirm your email address)

We don’t spam! Read more in our Privacy Policy

Leave a Reply